  • A. Decision. The Planning Board shall consider the application and the recommendations of the Administrative Officer. Within sixty five (65) days of the date the application was certified complete, the Planning Board shall either approve, approve with conditions, or deny the application. Failure of the Planning Board to act within the period specified shall constitute approval of the administrative subdivision plan, in which case a certificate from the Administrative Officer as to the failure of the Planning Board to act within the required time period, and the resulting approval, shall be issued on request of the applicant.

    B. Expiration of Approval. Approval of an administrative subdivision shall expire ninety (90) days from the date of approval unless a plat in conformity with such approval, including all fees, documents and conditions attached thereto, is submitted for signature and recording as provided in these Regulations within such time period.