§ 1015. General Construction Procedures and Inspections
The following procedures shall be followed in the construction of any subdivision or related improvement:
A. Pre-Construction Meeting. A pre-construction meeting shall be held with the Director of Public Works at least seven (7) days prior to the start of construction. The subdivider or developer, or a duly authorized representative, and the on-site project manager or contractor shall attend.
B. Inspections. Inspections and approvals by the Director of Public Works shall be required as follows:
1. Following installation of all underground drainage structures, systems and utilities prior to back filling;
2. Following the preparations of road sub-grade and shoulders;
3. Following the application and compaction of road surfacing materials and, if required, the completion of sidewalks;
4. Following completion of all improvements and installation of bounds; and
5. At periodic intervals to ensure compliance with the erosion and sediment control plan.
C. Notice and Fees. The developer shall notify the Director of Public Works when the project is ready for each of the above required inspections. Inspection fees shall be paid as established in Section 503.
D. As-Built Drawings. Upon completion of construction and all required improvements, and before the performance bond is released and the maintenance bond is accepted, the developer shall furnish one (1) complete mylar set, five (5) complete sets of blue line copies, and one (1) complete set of 11" × 17" reductions of "as built" drawings of the completed project, as well as a digital file, to the Administrative Officer.